WRF Hot Air Furnace for Ceramic Spray Dryers

October 25,2026    hxboiler    42

Every square metre of porcelain tile begins as a liquid. The slip leaves the ball mill at about 33 to 35 percent moisture, and before it can be pressed into a green body it must become a free flowing granulated powder at about 6 to 7 percent moisture. That transformation happens in the spray dryer, and the spray dryer lives or dies by its hot air source. If the air is not hot enough the tower loses tonnage, if it swings the powder moisture drifts, and if it is not clean the finished tile shows iron spots and specks that polish out as rejects. This article works through what a ceramic plant actually needs from its hot air source, why indirect heating is the right architecture for a white body plant, and how to size and install a unit from the WRF-Y(Q) series oil and gas fired hot air furnace range on a real spray drying duty.

The planning figures below suit body preparation lines of roughly 80 to 100 tonnes of dried powder per day, which is the size class of a single medium spray tower. They are estimates for engineering discussions; a final selection should always be confirmed against the slip density, tower geometry, altitude and ambient humidity of the actual site.

Why the Spray Dryer Depends on Its Hot Air Source

A spray dryer is a one pass evaporator. Fine droplets of slip are injected into a stream of hot air at the top of the tower, water flashes off in the two or three seconds of fall, and dry granules exit through the cone at the bottom while humid air leaves through the exhaust. The energy for all of that evaporation arrives as sensible heat in the air, so the furnace feeding the tower is effectively the engine of body preparation. Three characteristics decide whether it is fit for the duty.

First, capacity with reserve. The tower is rated in tonnes of powder per day, and that rating collapses quickly when inlet air temperature cannot be held because the furnace is saturated. Second, temperature stability. Powder moisture tracks tower outlet temperature almost linearly, so an inlet air source that holds within a few kelvin keeps the granulation within specification without operator intervention. Third, air cleanliness, because the air touches the product itself and later ends up pressed into the tile. An oil and gas fired indirect hot air furnace satisfies all three at once: it modulates cleanly on gaseous or light liquid fuel, holds outlet temperature automatically, and by design never lets combustion products touch the process air.

The Heat User Map of a Body Preparation Line

Before sizing, list every consumer of hot air around the tower. The table below shows a representative line with its neighbours.

UserAir temperatureLoad characterConsequence of a shortfall
Spray dryer tower inlet air250 to 300 degrees Celsius, some duties up to 350Continuous, dominant, tightly controlledTonnage falls, powder moisture rises
Green body dryer branch80 to 130 degrees Celsius mixed airContinuous between shiftsWet tiles crack before firing
Slip room and pump house heating15 to 25 degrees Celsius room airWinter, smallComfort and slip viscosity only
Plant hot water45 to 60 degrees Celsius via plate exchangerContinuous, smallStaff services
Tower start-up preheatAmbient to setpointLarge short peak, once per startSlow start-up, off spec first hours

Two features of this map drive the design. The tower is the only large load and it runs continuously for the full shift plan, so the furnace should sit near 70 to 80 percent of rating in steady operation with real reserve for start-up preheat. The green body dryer branch is small but cannot be allowed to freeze when the tower pulls hard, which is why both branches get independent control rather than sharing one duct by hand.

What Clean Hot Air Means in a White Body Plant

Ceramic powder is a white, iron sensitive product, and the defects caused by dirty process air are expensive precisely because they appear after pressing, firing and polishing. Indirect heating is the structural answer. In the WRF-Y(Q) concept the burner fires into a furnace core made of heat resistant SUS304 stainless steel, the flue gas stays inside that core and the multi pass plate heat exchanger, and the process air is heated on the outside of the exchange surfaces and delivered through an inlet air filter. Combustion products, sulphur and soot never enter the tower, so the granules leave with the same whiteness the slip had.

The range addresses the details that make indirect designs work in practice. The furnace core is SUS304 with a 150 millimetre insulation layer, so radiation losses stay low and the steel does not scale and shed oxide into the air path. A three circuit cross flow plate exchanger keeps the exchange surfaces accessible and the unit compact. A waste heat recovery option on the flue side lifts overall heat exchange efficiency above 90 percent and trims fuel consumption by 5 to 8 percent compared with a plain furnace, which on a continuously running tower is a meaningful annual sum. Clean air is not a slogan here, it is the reason a ceramic plant should not consider a direct fired solution for this duty.

The WRF and ZRFQ Range at a Glance

The catalogue header lists a standard delivered band of 0.6 to 2.4 MW rated heat power, while the model table covers fifteen ratings from 60 to 4,200 x 10,000 kcal per hour, which spans roughly 0.07 to 4.88 MW. Working pressure is atmospheric on the air side, the rated air outlet temperature spans 100 to 400 degrees Celsius, and the design fuel is natural gas or light oil. Verified figures from the product specification page are summarised below.

ModelHeat power (x10,000 kcal/h)Approx. output (MW)Natural gas (Nm3/h)Light oil (kg/h)Transport size LxWxH (m)
ZRFQ-5-YQ600.073.5-11.57-141.5x0.6x0.8
ZRFQ-10-YQ1200.1410-2813-262.6x0.9x1.2
ZRFQ-20-YQ2400.288-4115-332.7x1.0x1.3
ZRFQ-30-YQ3500.418-4115-332.5x1.1x1.45
ZRFQ-40-YQ5000.588-4115-333.5x1.2x1.55
ZRFQ-60-YQ7000.8120-8520-753.5x1.3x1.65
ZRFQ-80-YQ10501.2230-12030-904.0x1.4x1.75
ZRFQ-100-YQ12001.405-15035-1104.0x1.5x1.85
ZRFQ-120-YQ14001.6350-21067.5-177.14.0x1.7x2.05
ZRFQ-150-YQ17502.0450-26080-2204.9x1.8x2.2
ZRFQ-200-YQ24002.7990-320100-2905.2x1.9x2.3
ZRFQ-240-YQ28003.2650-36080-3295.6x2.0x2.4
ZRFQ-300-YQ36004.19100-450120-3605.6x2.05x2.5
ZRFQ-360-YQ42004.88100-450120-3605.6x2.1x2.6
ZRFQ-400-YQ42004.88100-450120-3606.0x2.1x2.6

The largest unit ships within a 6.0 by 2.1 by 2.6 metre transport envelope, which means even a 4.9 MW furnace travels as ordinary road cargo and lands beside the tower without special lifting plans. Fully automatic control keeps the drying temperature in a 60 to 220 degree Celsius band with automatic transition between high and low fire, and after flame off the burner fan continues for fifteen minutes to sweep and cool the chamber.

Sizing the Furnace in Four Steps

Step 1: convert the powder rating into an evaporation load

Per tonne of spray dried powder, the water balance is fixed by the two moisture points. Slip at 34 percent moisture and powder at 6.5 percent moisture give about 417 kilograms of water evaporated per tonne of powder. A tower rated around 86 tonnes of powder per day on a twenty hour plan therefore evaporates about 1,800 kilograms of water per hour.

Step 2: apply a specific heat consumption

Well maintained indirect spray drying installations run at roughly 3,200 to 3,500 kilojoules per kilogram of water evaporated, where the figure covers heating the slip droplets, evaporating the water and the shell and duct losses of the tower. At 3,300 kilojoules per kilogram, 1,800 kilograms per hour demands about 5.94 gigajoules per hour, or 1,650 kilowatts of useful heat delivered to the tower.

Step 3: add the satellite users, then diversity and margin

The green body dryer branch and winter services add a small continuous demand. Because the tower dominates and runs flat out while the others are intermittent, a diversity factor of 0.90 is realistic, followed by a 10 percent margin for fouling, altitude and humidity swings.

Step 4: select the model near 70 to 80 percent load

Pick the rating that puts the steady point in the modulating band of the burner. The table works the example end to end.

Worked example: one medium tower with green body dryer

LoadBasisDemand
Spray tower evaporation1,800 kg/h x 3,300 kJ/kg1,650 kW
Green body dryer branchContinuous mixed air users120 kW
Slip room and hot waterWinter services20 kW
Connected load
1,790 kW
Diversity at 0.901,790 x 0.901,611 kW
Margin at 10 percent1,611 x 1.101,772 kW design output
Model selectionZRFQ-200-YQ at 2,400 kWAbout 74 percent in steady running

ZRFQ-150-YQ at 1,750 kilowatts sits at 101 percent of the design output and is correctly rejected, because a furnace that must run flat out has no reserve for start-up preheat and no modulating room on mild days. ZRFQ-200-YQ carries the steady duty at about 74 percent, absorbs the tower preheat peak without strain, and still holds acceptable efficiency at partial load because the burner transitions between high and low fire automatically. For a plant planning a second tower, ZRFQ-240-YQ at 2,800 kilowatts is the step up to discuss before civil works begin.

Ducts, Mixing and Control Around the Tower

Holding tower inlet temperature

The tower inlet temperature is the loop that protects product quality, so it should be closed properly. The burner firing rate gives the coarse adjustment and a dilution air damper at the furnace outlet gives the fine trim, which lets the control catch fast changes in slip flow without hunting the burner. Furnace outlet thermocouples need annual calibration, and the automatic control that holds drying temperature in its 60 to 220 degree Celsius band should be checked against a reference probe at commissioning.

The green body dryer branch

Green tiles are dried on a separate temperature level, so the dryer branch takes its own air from a second take-off and mixes it down to 80 to 130 degrees Celsius with ambient air through a motorised damper. This keeps a slow drying curve available even while the tower is at full pull, and it means the dryer branch can run overnight on low fire without dragging the tower off temperature. Isolation dampers on both branches allow either user to be shut for service without stopping the furnace.

Duct practice and safety interlocks

Keep the furnace close to the tower, because every metre of hot air duct costs temperature and money; insulate with 100 to 150 millimetres and fit expansion bellows for the 250 to 300 degree Celsius duty. On the safety side the interlock set should include airflow proven before burner start, a high temperature cut out on the furnace outlet, flame supervision on the burner, and the standard post shutdown sweep in which the fan continues for fifteen minutes to cool the chamber. These are catalogue features of the range, but they must be wired, tested and documented on site like any other safeguard.

Fuel Consumption and Operating Cost Planning

Planning values for one megawatt hour of useful heat delivered to the tower are listed below, assuming a net utilisation of about 92 percent after duct and exchanger losses; sites with the waste heat recovery option do better than these figures.

FuelApproximate consumption per MWh useful heatPractical notes
Natural gasAbout 109 Nm3Preferred where the pipeline reaches the cluster
LPGAbout 85 kgSuits non pipeline sites with tank supply
Light oilAbout 92 kgStore warm and filter; watch sulphur content

For the worked example the tower consumes about 33 megawatt hours of useful heat in a twenty hour day, which is close to 3,600 cubic metres of natural gas or the light oil equivalent. In ceramic clusters the gas grid is usually available, which keeps fuel cost predictable; where it is not, LPG or light oil are fully supported design fuels of the range, and the burner selection changes rather than the furnace.

Installation and Commissioning Checklist

ItemWhat to verify
SitingFurnace close to the tower, level foundation, clear burner pull out space, transport envelope checked against the access road
Gas trainRegulation skid sized for maximum flow, leak test, two automatic valves plus vent, correct governor setting
Air pathInlet filter fitted with a differential pressure gauge, duct joints airtight, insulation complete, expansion bellows free
InstrumentationTower inlet and outlet thermocouples calibrated, dilution damper travel confirmed, furnace outlet high limit tested
ControlsHigh low fire transition observed, cascade tower inlet control tuned, dryer branch mixing damper tuned
SafetyAirflow proving, flame supervision, fifteen minute post shutdown sweep, emergency stop tested
Site factorsAltitude and summer humidity checked against the air mass calculation, fuel consumption re-estimated for the worst month

Maintenance Calendar

IntervalTask
DailyLog furnace outlet and tower inlet temperatures, burner behaviour, filter differential pressure
WeeklyInspect filter media, check damper actuators, test safety cut outs, inspect duct insulation hot spots
MonthlyCheck burner electrodes and nozzle, inspect gaskets and door seals, verify thermocouple readings against a reference
QuarterlyClean exchange surfaces where accessible, review combustion flue gas readings, tighten electrical connections
AnnuallyFull exchanger inspection, furnace core weld and scale survey, insulation repair, complete interlock test with records

Supplier Qualifications, Custom Engineering and OEM

A hot air furnace feeding a spray tower runs thousands of hours a year at high temperature, so the manufacturer behind it should prove more than a catalogue. Henan Hengxin Boiler Co., Ltd. manufactures under a special equipment production licence and holds ISO9001 and ISO14001 certification with 3A enterprise credit standing, and the certificates page lists the documents for review. Building materials and drying duties are established application fields of the product platform, as the application pages record. Standard models cover the fifteen ratings in the table above, and the company also builds to customer drawings and develops custom configurations for unusual capacity points, special duct arrangements, integrated dilution and mixing skids, and control integration with the tower PLC or a plant DCS. For a ceramic project, supplying the tower rating, slip moisture points, altitude and fuel situation is usually enough for a factory proposal with layout, air flow estimate and delivery time.

FAQ: Questions Ceramic Plant Buyers Ask

Can one furnace serve both the spray dryer and the green body dryer?

Yes. The worked example above includes both users in one connected load: the tower takes its high temperature branch straight from the furnace, while the green body dryer draws a separately mixed branch at 80 to 130 degrees Celsius. Independent control valves and isolation dampers let each branch hold its own curve, and the sizing margin covers running both at once.

What air temperature does porcelain spray drying actually need?

Most porcelain and stoneware towers run with inlet air at 250 to 300 degrees Celsius, and some high tonnage installations go up to about 350 degrees Celsius. The ZRFQ range delivers 100 to 400 degrees Celsius at atmospheric pressure, so the whole duty sits comfortably inside the catalogue window with room for start-up preheat.

Why indirect heating instead of a direct fired burner for ceramic powder?

Direct firing mixes combustion products into the process air, which adds moisture, sulphur compounds and soot to air that touches a white, iron sensitive product, and it also makes tower humidity control harder. Indirect heating keeps the flame inside a SUS304 core and the flue gas inside the plate exchanger, so only clean filtered air reaches the droplets, and speck defects attributable to the air source are eliminated at the design level.

How much fuel does a medium tower consume per day?

For the example tower evaporating 1,800 kilograms of water per hour over twenty hours, about 33 megawatt hours of useful heat per day, close to 3,600 cubic metres of natural gas on the planning values above. Actual consumption follows slip moisture, tower condition and ambient humidity, which is why the commissioning checklist asks for the worst month to be re-estimated rather than the average one.

Start with the Tower Heat Balance

Ceramic plants that move spray drying to a properly sized indirect hot air furnace almost always report the same two gains: powder moisture and granule quality become repeatable because tower inlet temperature stops hunting, and speck claims stop appearing because the process air is genuinely clean. Both begin with an honest heat balance of the tower, not with a brochure. Henan Hengxin Boiler Co., Ltd. supports that first step with application engineers who size hot air systems across building materials, grain, food, chemical and drying duties, and the company welcomes drawings and data for custom development. Send the tower rating, the slip and powder moisture points and the fuel situation, and a sizing proposal with layout and fuel figures follows for review before any commitment is made.

RECOMMENDED PRODUCTS

  • 1Rated Heat Power(MW)0.35-7
  • 2Rated Working Pressure(MPa)1.0
  • 3Rated Outlet/Return Temperature(℃))115/70
  • 4Design FuelCoal Biomass Fuel
  • 1Rated Heat Power(MW)0.35-14
  • 2Rated Working Pressure(MPa)0
  • 3Rated Outlet/Return Temperature(℃))85/60
  • 4Design FuelCoal Biomass Fuel
  • 1Rated Steam Capacity(t/h)1-20
  • 2Rated Working Pressure(MPa)1.0-2.5
  • 3Saturated Steam Temperature(℃))184-225
  • 4Design FuelNatural Gas,Light Oil,Heavy Oil etc.
  • 1Rated Output(t/h)0.5-4.0
  • 2Rated Steam Pressure(MPa)1.0-1.6
  • 3Steam Temperature(℃))184-204
  • 4Apply FuelDiesel oil、Heavyoil、 Natural gas
  • 1Rated Heat Power(MW)120-600
  • 2Rated Working Pressure(MPa)1.0
  • 3Max Working Temperature(℃))320
  • 4Design FuelBiomass Fuel
  • 1Rated Steam Capacity(t/h)4-20
  • 2Rated Working Pressure(MPa)1.25/2.5
  • 3Saturated Steam Temperature(℃))194-225
  • 4Design FuelCoal Biomass Fuel

Inquiry

Contact

Hengxin
Taikang Hengxin Boiler Co., Ltd. is located in Taikang County, Zhoukou City, Henan Province, the company was founded in 2016, is a specialized in boiler,pressure vessel products research and development, design, production, sales, installation, transformation and aseries of services. 7 years of development, Hengxin boiler has established a complete product line.The product line includes 8 kinds of oil and gas boiler, coal boiler, biomass boiler, hot blast stove, heat conductionoilboiler,electric boiler,waste heat boiler, circulating fluidized bed boiler,pressure vessel,28productseries,morethan 300models.Products cover agriculture,forestry,husbandryand fishery, food, textile, manufacturing, chemical, building materials, metallurgy and minerals, power supply and heating and many other industries. Hengxin Boiler,asone of the earliestenter prisesengaged in the boiler industry in China,was the first toobtain the B-classboiler manufacturing license issuedby the General Administration of Qua...